Construction Project · Report 04

PASNI ROAD

Funded by Abu Dhabi Fund for Development

Construction of Road from Makran Coastal Highway to Pak Oman Hospital, Pasni Interchange & Palace · RD 0–15 KM. A 9-month Fixed-Price Lump Sum contract executed by Rustum Associates–Imaad Builders & Developers JV.

Client PASNI ROAD PROJECT
Length 15 km
Duration 9 months
Start Date 15 Feb 2026
Target Date 15 Nov 2026
Reporting Period Week 11 of 39 15 Feb 2026 — 30 Apr 2026
Actual Project Progress
0.0%
0% 100%
% Complete
0.0%
Earned of total scope ▲ on plan
SPI · Schedule
0.00
Ahead of schedule +0%
I

Monthly Site Images

March · April
Photo Progress

Monthly Site Images

Auto sliding until manual change
II

Cumulative Progress

39-Week Timeline
S-Curve Analysis

Planned vs Actual Progress

III

Presentation Slides

Executive Briefing
Executive Review

Management Slides

Auto sliding · click arrows to take control
IV

EVM Performance

Earned Value Management
Activity Categories

Planned · Earned · Actual Value

Project Performance

Key Indicators

BAC
Budget at Completion
AC
Already Spent
REM
Remaining Budget
V

Performance Detail Charts

EV / AC Cumulative Flow
Weekly Tracker

Cumulative EV / AC Flow

A

Activity Register

22 Activities · Click row to expand
S.No Category Activity Budget Wt % Plan % Actual % Progress Status
D

Data Input

Excel Linked · Auto Refresh
Edit values below · changes update charts immediately
Project Sheet Values

Live Inputs Summary

Weekly Tracker

Current Week Input

Activity Master · Budget · EVM

Activity Data Editor

S.No Category Activity Name Budget (PKR) Plan % Actual % EV (PKR) AC (PKR) CV (PKR)
Admin · Media

Upload Images & Slides

Site Photos

Management Slides
PASNI ROAD PROJECT · Live Dashboard